The NSIP Consenting Process: Why Securing a DCO Is Only Half the Work
Key TakeawaysA Development Consent Order sets obligations rather than a finished licence to build, as pre-commencement
Press Release Disclaimer: This is a press release distributed through the XPR Media network. It has not been independently verified by our newsroom.

![]()

Key Takeaways
- A Development Consent Order sets obligations rather than a finished licence to build, as pre-commencement requirements must be discharged before work starts.
- Early, proactive management of consent and stakeholder risk costs far less than fixing problems after they appear.
- Commitments are scattered across many documents, so a register of owners and due dates becomes essential once construction begins.
- Contractors joining after consent can inherit conditions they never negotiated.
- Land referencing, access negotiation and compulsory purchase continue well past consent and can decide whether a scheme stays on programme.
Winning a Development Consent Order (DCO) feels like the finish line after years of examination, consultation and scrutiny. For a project director taking a Nationally Significant Infrastructure Project (NSIP) into construction, the reality is less tidy. A DCO sets the terms under which a scheme can proceed, but turning that formal permission into something a contractor can build against takes separate, ongoing effort. the team at Evermark Advisory, UK, works with promoters and developers at this point, helping keep commitments, communities and land matters aligned with the delivery programme – they share further insights below.
A DCO Is Not Permission to Build
A Development Consent Order grants permission for a project to go ahead, but it arrives with requirements that must be satisfied before work can lawfully begin. Many act as gates: a final traffic management plan might need local authority sign-off, and construction cannot start on the elements it covers until the authority agrees. Treating consent as the end of the planning process rather than the start of a compliance phase is one of the most common ways programmes lose months.
Carrying out development in breach of a DCO’s terms without reasonable excuse is a criminal offence under the Planning Act 2008, punishable by a fine. The larger risk, though, is a stalled site, a damaged relationship with a discharging authority, or a requirement renegotiated mid-programme. Practical permission to build is earned in the months of discharge and coordination that follow consent.
Why Pre-Commencement Requirements Stall Sites
Pre-commencement requirements exist to make sure the detail behind a consented scheme is properly worked through before diggers move. They cover everything from ecological mitigation to highways works, and each one typically needs a named authority to confirm it has been satisfied. Getting this stage wrong is one of the most frequent causes of delay on NSIP schemes, often because the groundwork for smooth discharge was never laid during the application itself.
Naming the Discharging Authority Before Consent
Before a DCO is even granted, applicants should make sure each requirement is precise, enforceable, necessary, relevant and reasonable, and should name the specific body that will receive each discharge application. Leaving this vague invites confusion later, when the project team is trying to work out who actually has authority to sign off a given document. A requirement that clearly identifies its discharging authority from the outset removes an entire category of argument once construction teams are under programme pressure.
Tight Discharge Timescales
Discharge timescales are fixed in each order, but many DCOs give requirement consultees around 10 working days to request further information and around 15 working days to comment once they have it. Under many orders, a planning authority that does not ask for more information in time is treated as having enough to decide. Missing these windows, or submitting incomplete applications, is where many discharge timelines quietly unravel.
The Cost of Getting Requirements Wrong
Local authorities carry real responsibility after consent, including discharging requirements, monitoring works on site, taking enforcement action and responding to proposed changes to the order. Treating this relationship as a formality tends to slow discharge applications and thin goodwill when the programme needs cooperation most. Building a constructive working relationship with each discharging authority from the start of the post-consent phase pays for itself across the life of the project.
Keeping a Commitments Register That Holds Up
Every NSIP accumulates a long trail of commitments made to secure consent, and keeping track of them properly is one of the less glamorous but most important disciplines in post-DCO delivery.
Why Commitments Scatter Across the Project Record
Commitments made before consent rarely live in one place. They turn up in consultation reports, the environmental statement, statements of common ground, examination records, side agreements and the DCO itself. A promise made to a community group can carry as much weight in practice as a formal requirement, yet is far easier to lose track of, leaving teams to rediscover obligations mid-construction.
Tracking Commitments From Consent to Decommissioning
A useful commitments register follows a project from planning through design, procurement, construction, operation and decommissioning. For each commitment, it records how it was secured, how it will be discharged, when it falls due, who owns it, and when compliance was achieved. Keeping it updated after consent, rather than treating it as an examination artefact, lets a project demonstrate compliance clearly if challenged.
When Delivery Teams Change After Consent
It is common for the organisation that takes an NSIP through examination to be different from the one that eventually builds it, and that handover point carries its own risks.
Contractors Inheriting Conditions They Didn’t Negotiate
When the delivery contractor changes after the DCO is granted, the incoming team can be bound by a construction method it had no part in shaping. This is a particular pressure point for Tier 1 contractors, who often arrive after conditions, commitments and stakeholder relationships are set. Promoters can reduce this friction by involving likely delivery partners during consenting, so they understand the DCO’s practical implications before they are contractually bound.
Coordinating Post-DCO Approvals Without Losing Time
Beyond the requirements in the order, a project typically needs further post-DCO approvals covering matters such as drainage and cabling. Poor coordination across approvals running in parallel can cause significant delay. Structured coordination with local planning authorities on the whole set, rather than treating each as a separate transaction, keeps the critical path moving.
Land and Stakeholder Work Doesn’t Stop at Consent
Consent decisions are shaped heavily by the relationships built with communities, consultees and landowners long before the examination begins, and those relationships need just as much attention once construction is underway.
Mapping Consultees, Landowners and Communities Early
Engagement works best when it runs continuously from inception through to operation, rather than tapering off after consent. A practical starting point is mapping stakeholders and understanding their interests, influence and concerns, so effort is directed where it matters most. Community liaison officers and community liaison groups can maintain contact once construction starts, giving a channel for honest explanation of construction impacts and the mitigation the project offers.
Keeping Land Access and Compulsory Purchase on Programme
Land that still needs to be acquired, accessed or crossed can remain a live risk throughout the works. Land referencing, access negotiation, compulsory purchase and landowner relationships all continue past consent, and any one going wrong can halt progress on site. Treating land and access as a parallel programme stream, with its own milestones, keeps these risks from turning into surprises.
Practical Permission Is Won Long Before Breaking Ground
The real test of a consented NSIP sits in everything that follows the DCO decision: requirements discharged cleanly, commitments tracked honestly, delivery teams brought up to speed, and land and stakeholder relationships maintained. Project directors who treat these as live workstreams from day one tend to see fewer surprises on site. As a practical next step, building a clear register of post-consent commitments and requirements early gives any delivery team a stronger footing for construction.